Projects ➔ Planning ➔ Tasks
In order to perform the work that needs to be done in a project, tasks need to be created. Tasks are automatically generated when creating certain orders or requests. In this screen, you can manually create tasks. You many need to manually create tasks in the following scenarios:
After the tasks are created, the tasks have to be planned or assigned to people. Initially, all tasks are not planned to any person unless a person is specified in an order or request line. For more information, see Overview of resource planning and tasks and How-to: Managing projects.
The information in this document is based on product update 406 and higher. If you have versions lower than this, certain features explained here will not be applicable.
Keep in mind:
Type or select a project to create a task for this project.
Type or select a date or range of dates to create a task on or within this date(s). By default, the current date is selected as the start date.
Type the description for the task.
Type the quantity of the item required to perform the task.
The unit of measurement will be displayed based on the selection at Item, and cannot be edited.
Type or select an hour item to be linked to the task. Once selected, the unit of measurement defined in the corresponding hour item maintenance screen will be displayed at Unit.
Type or select a person to plan this person for the task. Once selected, the cost center of the person will be displayed at CCtr.
Type or select a cost center code to plan the task to this cost center without specifying a person. Once selected, the name of the cost center is displayed on the left of the box. This information can only be edited if you do not define a person at Person.
Type or select a request to link this request to the task. Once selected, the description of the request is displayed in the next box.
Click to attach a file to the task.
Type any extra description of the task, if required.
Price displays the total price of the item selected at Item based on the quantity entered at Qty.
Amount displays the total amount of the cost incurred.
G/L displays the general ledger account selected at Realizations in the Financial tab of the corresponding hour item maintenance screen.
Click this to obtain an overview of resource planning and tasks. For more information, see Overview of resource planning and tasks.
Click this to define extra information for the recurring task.
Click this to save the task.