Creating and maintaining production orders - Production order lines section - Extra charges tab
This screen is displayed when New or Open
is clicked at Manufacturing ➔ Entries ➔ Production orders.
Fields
This tab defines details of the extra charges items.
Step
Type or select a step to link the part item to a particular
step in the production routing. It is a mandatory field and denotes a specific
stage in a manufacturing process. This field is available only if the following
conditions are met:
- The Operations check box is selected under Manufacturing
settings at System ➔ General ➔ Settings.
- The Explode – Fulfillment check box is not selected
under the Purchase/ Sales tab in the item maintenance (go to Manufacturing ➔ Setup ➔ Items,
select the relevant item and click Open).
Item
Type or select the item needed to produce the finished good.
By default, the items listed in the BOM are automatically displayed after you
have entered the production order information in the production order header.
Version
By default, the version displayed is the version number for
the BOM version of the finished good. This information is displayed
automatically and is not available for editing.
Description
By default, the description displayed is the description for
the corresponding item. This information is displayed automatically and is not
available for editing.
Printed
By default, the print status is displayed automatically and
is not available for editing. You will see a check mark if the production order
has already been printed.
Note: The Printed column is automatically
checked if you do not select the Production order check box in the Print
section under Manufacturing settings at System ➔ General ➔ Settings.
Start date
Type or select a date when the item is prepared for the
production order. By default, the start date displayed is calculated from the
production order start date (in the production order header) and the start of
the item’s lead time. The lead time for a purchase item is the purchase lead
time whereas the lead time for a manufactured item is the item’s BOM lead time.
End date
Type or select a date when the item is expected to be ready
for production. By default, the end date displayed is calculated from the item
start date (in the production order lines) and the item’s lead time. The lead
time for a purchase item is the purchase lead time whereas the lead time for a
manufactured item is the item’s BOM lead time.
Cost center
Type or select a cost center to link the item to the cost
center.
Person
Type or select a person code to assign a person to the
item, labor hour, or machine capacity. By default, the person code displayed
is the person code registered to the current user’s login ID.
Pos. no.
Type the position number where the item can be found in the
warehouse, if available.
Amount
By default, the amount displayed is the total cost for the
planned quantity of the item. This information is displayed automatically and
is not available for editing. The cost of the item is dependent on the type of
the item. For example, if the item is a machine hour, the amount is the cost
per unit of machine hour multiplied by the planned quantity of machine hours. If
the item is a subassembly, the amount is the subassembly item cost per unit
multiplied by the planned quantity.
Click this column to edit or insert a new note in the
production order. In the Note screen, type the note, click Save
and then Close to exit.
Click this column to edit or insert an attachment in the
production order. In the Attachment screen, select an attachment by
clicking . Then, type a description and click
Save.
Project
By default, the project information is not available for
editing. The project information is automatically filled in with the production
order code after the production is created and saved.
Related document
Main Category: |
Attachments & notes |
Document Type: |
Support - On-line help |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
17.644.309 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
390 |
Attachment: |
|
Disclaimer |