One moment please...
 
 
Exact Globe+   
 

Defining start time for sorting of operations

Introduction

Introduction

You can define the start time of the operations involved in a production order. To do this, go to Manufacturing/Entries/Operations control. Define the relevant criteria, and click Refresh. You will see a list of production orders. Select the production order you want to maintain and click the Sorting sequence button. By defining the start time of operations, the operations will be sorted automatically according to the defined start time within the same production order.

This functionality is enabled when you select the Operations check box at System/General/Settings/Manufacturing settings, Operations section.

Description

Once the Sorting sequence button is clicked, the following options are available:

Start date

This displays the start date of the operation in the production order. This cannot be edited.

End date

This displays the end date of the operation in the production order. This cannot be edited.

Start time

Type the start time of the operation involved in the production order.

Buttons

OK

Click OK to save the defined start time for the operation. This will automatically sort the operations within a production order according to the defined start time.

Cancel

Click Cancel to not save the defined start time for the operation.

Related documents

     
 Main Category: Attachments & notes  Document Type: Support - On-line help
 Category:  Security  level: All - 0
 Sub category:  Document ID: 16.095.007
 Assortment:  Date: 26-09-2022
 Release:  Attachment:
 Disclaimer