Introduction

This page displays the details of the selected operations and steps. From this page, you can also perform actions like viewing details of the Bills of Materials (BOM) and routing of the operations, registering the time entries for your labor and machine hour items, and more.

Roles and rights

To access this page, the Shop floor control role is required. In addition to that, a few requirements need to be met. For more information, see the Roles and rights section in Logging in to Shop Floor Control via Exact Synergy Enterprise.

Notes:

  • For more details on function rights, go to System à Setup à Security à Function rights.
  • For more details on roles, go to System à Setup à Security à Roles.

What version are you using?

The information in this document is based on product update 252.

How do I view the details of operations?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.

How do I view the Bills of Materials (BOM) of the operations?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.
  5. Click BOM. The BOM pop-up page will be displayed.

How do I view the routing details of the operations?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.
  5. Click Routing. The Routing pop-up page will be displayed.

How do I register the time entries for the labor and machine hour items?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.
  5. Click Next. The Time registration page will be displayed.
  6. Click Start next to the respective labor or machine hour item to start the operation. Once you have clicked Start, Stop will be displayed. Click Stop to stop the operation.

Keep in mind:

  • When there are no labor or machine hour items to be realized, after clicking Next at step 5, the Issue materials page will be displayed.
  • When there are no labor or machine hour items to be realized and no materials to be issued, after clicking Next at step 5, the Quantity complete page will be displayed.
  • When there are no labor or machine hour items to be realized, no available materials to be issued, and the operation is the last operation in the production order, after clicking Next at step 5, the Production receipt page will be displayed.

How do I register the quantity of materials used for the operations?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.
  5. Click Next. The Time registration page will be displayed.
  6. Click Next. The Issue materials page will be displayed.
  7. Define the information required.
  8. Click any of the buttons to save the information.

Keep in mind:

  • When there are no labor or machine hour items to be realized, after clicking Next at step 5, the Issue materials page will be displayed.
  • When there are no labor or machine hour items to be realized and no materials to be issued, after clicking Next at step 5, the Quantity complete page will be displayed.
  • When there are no labor or machine hour items to be realized, no available materials to be issued, and the operation is the last operation in the production order, after clicking Next at step 5, the Production receipt page will be displayed.
  • When there are no materials to be issued, after clicking Next at step 6, the Quantity complete page will be displayed.
  • When there are no materials to be issued and the operation is the last operation in the production order, after clicking Next at step 6, the Production receipt page will be displayed.

How do I define the quantity completed for the operations?

  1. Select the SFC Interface check box.
  2. At Operation, select an operation.
  3. Click Login. Once you have logged in, the production orders with the steps that will be executed on the selected operation will be displayed.
  4. Click on a row to view the details of the corresponding operation. The Operation details page will be displayed.
  5. Click Next. The Time registration page will be displayed.
  6. Click Next. The Issue materials page will be displayed.
  7. Click Next. The Quantity complete page will be displayed.
  8. Type a number at Quantity completed.
  9. Click any of the buttons to save the quantity.

Keep in mind:

  • When there are no labor or machine hour items to be realized, after clicking Next at step 5, the Issue materials page will be displayed.
  • When there are no labor or machine hour items to be realized and no materials to be issued, after clicking Next at step 5, the Quantity complete page will be displayed.
  • When there are no labor or machine hour items to be realized, no available materials to be issued, and the operation is the last operation in the production order, after clicking Next at step 5, the Production receipt page will be displayed.
  • When there are no materials to be issued, after clicking Next at step 6, the Quantity complete page will be displayed.
  • When there are no materials to be issued and the operation is the last operation in the production order, after clicking Next at step 6, the Production receipt page will be displayed.

Buttons

Fields

Related documents

     
 Main Category: Support Product Know How  Document Type: Online help main
 Category: On-line help files  Security  level: All - 0
 Sub category: Details  Document ID: 23.975.902
 Assortment:  Date: 11-11-2013
 Release: 251  Attachment:
 Disclaimer

Attachments
OH252-ViewingdetailsofoperationsintouchscreenUI-final.docx 34.4 KB View Download