A project can be defined as a temporary or non-repetitive attempt that utilizes various resources to achieve a clear and unique objective such as a product or service, within a defined period, scope, and requirement. At this screen, you can create or maintain a project. Each project contains its own data which you can register and maintain in its own project master card. The information of the project is divided into several categories which is presented under different tabs: Basics, Planning, Activities, Related, Members, Doc., Rates, Hours, Pur./Inventory, Inv., Extra, and Log. When defining a new project, you should at least enter data under the Basics and Extra tabs. The Basics tab is where most of the static information of the project is recorded and maintained. The other tabs are for viewing and entering information for established projects. Once saved, you can view or maintain the project at Projects/Projects/Maintain projects.
You can also generate projects from quotations, sales/purchase orders, and production orders if you have the relevant modules in your license. The projects will be generated based on the following scenarios:
The system will generate two projects:
After a project is created, you can create a budget for the project based on the relevant budget scenario at System/Finance/Budgets. Once a budget is created, you can allocate it to the child project, periods, items, or resources. In order to perform the work that needs to be done in a project, tasks need to be created. For more information, see Creating and Maintaining Tasks and How-to: Managing Projects.
The information in this document is based on product update 397. If you have versions lower than this, certain features explained here will not be applicable.
If you are viewing a project, this displays the code and description of this project as defined at Project and Description respectively, under the Basics tab. As such, the information cannot be edited here. However, if you are creating a new project, no information is displayed.
This displays the manager of this project as defined at Manager under the Basics tab. As such, the information cannot be edited here.
This displays the status of the project as defined at Status in the MRP section under the Basics tab. As such, the information cannot be edited here.
Click this to add an account for the project. Once selected, the name, type, status, and address of the creditor or debtor will be displayed.
Click this to delete an account from the project.
This tab should contain most of the static information of a project. When defining a new project, you should at least enter data under this tab, apart from the Extra tab.
Select one of the following to define this project with the corresponding type:
Note: You can change the project type among Fixed, Time & Material, Internal, Production, and Training before it is saved. Upon saving, you can only interchange the project type between a Time & Material and Fixed until an actual transaction is linked to the project.
Type a unique alphanumeric code to identify the new project. You can type up to 20 characters. This information is mandatory. Once you have saved this project, you can only recode using the Recode functionality. This code depends on the type of project created.
Note: If you are creating a child project by linking it to a parent project, and then saving it without typing a code, the system will automatically define the code as ‘PARENTCODE.00X’, whereby ‘PARENTCODE’ is retrieved from the code of the parent project and ‘X’ indicates the level of children. For example, if the parent project code is ‘PROJECT’, then the child project code is ‘PROJECT’.001’ when creating the first level child project or ‘PROJECT’.002’ when creating the second level child project. However, if you have defined the code before selecting a parent project, the code will not be overwritten by the system.
Type a description of the project. This information is mandatory.
Type or select a resource to assign this resource as a manager for this project. This information is mandatory. By default, the resource who is currently logged on the system is pre-filled when creating a new project. Once selected, the resource ID and name will be displayed, and the corresponding cost center will be automatically pre-filled at Cost center.
Note: A project manager has total management control of the overall operations of a project. Among his important roles are planning tasks to resources, realizing the hours on behalf of the resources, authorizing the realizations, and adding or removing project members from a project.
The system will automatically pre-fill the cost center based on the project manager defined at Manager. To edit, type or select a different cost center to link this cost center to the project. Once selected, the cost center code and description will be displayed.
Type or select a project to link the project as a parent for this project. Once selected, the code and description of the project will be displayed, and Project will be pre-filled by the system. For more information, see Project, above. However, if you have defined the code before selecting a parent project, the code will not be overwritten by the system.
Note: Parenting allows several sales orders to be grouped together. As such, a high-level monitoring of all the related projects can be obtained from a single overview. Once a text is typed, the Open button is enabled.
Click this to view the details of the parent project.
Note: This button is enabled only when you have entered the parent project in the Parent box.
Type or select one of the following statuses to define the project accordingly. By default, Proposed is displayed when creating a new project.
Note: If Time & Material or Fixed is selected at Type and the sales order linked to the project has been removed by the logistic MRP cleaning up tool, the field is disabled when Completed is selected. For more information, see How-to: Cleaning Up Logistic MRP Records.
Type or select the planned start and end date of the project. The total number of days planned for the project will then be calculated and displayed accordingly. If you leave this blank, the system will fill in the current date as the planned start date and the same date of the next month as the planned end date.
Type or select an item to link this item as an output of the project. Once selected, the item code and description will be displayed. Leave this blank if you do not wish to link any item as an output of the project. Different rules are applicable for the Training and Internal projects as follows:
Select this check box to include the information of the child projects in the project master card.
Select one of the following options to define the WIP method to calculate the profit of the project:
Percentage of completion (PoC) = (Actual revenue / Forecast revenue) x 100%
Suggestion of WIP (Change) = [Actual cost – (PoC x Forecast cost)] – WIP current
If Revenue forecast > Actual revenue, Percentage of Completion (PoC) = 0%, then,
Suggestion of WIP (Change) = (Actual cost – Actual revenue) – WIP Current
If Revenue forecast < or = Actual revenue, Percentage of Completion (PoC)= 100%, then,
Suggestion of WIP (Change) = – (WIP Current)
If Actual revenue = 0, then
Suggestion of WIP (Change) = Actual cost – WIP current
If Actual revenue <>0, then
Suggestion of WIP (Change) = Cost actual – [Qty invoiced x (Actual cost/Qty of item)] – WIP current
If (Actual cost / Qty of item) = 0, then
Suggestion of WIP (Change) = Actual cost – (Qty invoiced x Cost price) – WIP current
Suggestion of Recognized Costs (Change) = Qty invoiced x (Actual cost / Qty of item)
Note: If the item is a text item with zero standard cost price, the actual cost in the formula will be the cost from invoice.
Percentage of completion (PoC) = (Actual cost / Budget cost) x 100%
Suggestion of WIP (Change) = [(PoC x Budget revenue) – Actual revenue] – WIP current
Note: This method is available only if you have SE1050-E-Budget in your license.
Percentage of completion (PoC) = (Actual revenue / Budget revenue) x 100%
Suggestion of WIP (Change) = [Actual cost – (PoC x Budget cost)] – WIP current
Note: This method is available only if you have SE1050-E-Budget in your license. If you select any WIP method other than Percentage of completion cost recognition or Percentage of completion revenue recognition, you will see Percentage complete besides Status in the MRP section. Here, you can type the percentage of completion of the project. Only figures between 0.00 and 100.00 are acceptable. You can define the default WIP method at WIP method in the WIP method section at Project settings.
Result = (Actual revenue - WIP revenue) - (Actual costs - WIP costs - WIP others)
Result + WIP = Actual revenue - Actual cost - WIP production
Type or select a general ledger account for the work in progress. Once selected, the general ledger account number and description are displayed.
Note: This option is available only when you are creating a Production project.
This displays the number and description of the sales order linked to the project.
Note: This is available only when you are creating a Time & Material or Fixed project.
Type or select a warehouse to link this warehouse to an Internal or Training project. Once selected, the warehouse code and name is displayed. For Time & Material, Fixed, or Production project, this displays the number and description of the sales order linked to this project. This information cannot be edited for Time & Material, Fixed, or Production project.
Select one of the following options to compress the sales order lines with hour items, linked to this project. Note: The options are available only when you are creating a Time & Material project. However, it will no longer be available once a realization is authorized.
This section displays the terms of payment as defined in the sales order linked to the project.
Note: This section is available only for Time & Material or Fixed project and when the corresponding sales order is authorized.
Click this to generate an invoice for the selected term of payment.
Note: This is enabled only when a term of payment which is yet to be invoiced is selected.
Click this to insert a timestamp when adding notes to the project maintenance card.
Click this to insert a picture to the project master card.
Click this to delete the picture from the project master card.
Note: This is available only if you are viewing a project with a picture.
This section displays the planning, actual, and recognized amount of the revenue, costs, WIP, result, margin, and purchase/production of the project. Different financial information will be displayed, depending on the defined criteria. The descriptions for WIPs are summarized in the following table:
Different sets of buttons will be displayed when you are:
Apart from that, all buttons will be disabled when you are creating a new project, except for the Save and Close buttons.
Click this to obtain an overview of work in progress of projects to be generated or completely released. For more information, see Overview of Work in Progress of Projects to be Generated or Completely Released.
Note: This button is enabled only if you select other than No: WIP at WIP method, and functioning if you have defined the general ledger accounts for WIPs at Project settings.
Click this to link the appropriate commission item to a single or multiple sales orders. In the Apply rules screen, click Assortments to select the assortments which the items are linked to (if needed) and then click Close. Click Refresh to update the commission item list based on the defined criteria and then click Start to generate the selected commission assigned to the selected sales orders, or click Close to exit.
Note: This button is available only in a Fixed or Time & Material project.
Click this to automatically recalculate all the invoice proposals linked to this project simultaneously when any rates or discounts have been changed.
Note: This button is available only in a Fixed or Time & Material project, with authorized hour(s).
Click this to view or maintain the resource planning and tasks linked to this project. For more information, see
Click this to generate the graph of the actual revenue and costs of this project in Microsoft Excel.
Click this to view the transaction card of this project.
Click this to view the debtor master card linked to this project.
Click this to view or maintain the sales order linked to this project.
Note: This button is available only for Fixed or Time & Material project.
Click this to complete this project and update the status to Completed.
Note: You can only complete this project if all its child projects and the linked sales orders, invoices, internal use requests, and purchase orders are completed.
Click this to save the project.
Click this to exit.