Exact Visual scheduler - Clearing manual locks on production operations
Menu path
Manufacturing ➔ Planning ➔ Visual scheduler
Introduction
In this screen, you can remove any manual locks on the production operation. You will not be able to schedule a production operation if it is locked.
A production operation will be locked if any of the following occurs:
- The production operation is moved.
- The scheduled start or end time is changed.
- The production operation was approved.
What version are you using?
The information in this document is based on product update 405 and higher. If you have versions lower than
this, certain features explained here will not be applicable.
How do I clear the manual lock of a production operation?
- Click Op. zoom in at the toolbar.
- Once you are in the Operation zoom in form, right-click on the production operation that has been locked.
- Click Clear manual locks.
Keep in mind: Alternatively, you can select a production operation in the Operation zoom in form, click Actions, and then click Clear manual locks.
Related documents
Main Category: |
Attachments & notes |
Document Type: |
Online help main |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
22.668.470 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |