Overview of Exact Visual scheduler

Menu path

Manufacturing Planning Visual scheduler

Introduction

Exact Visual scheduler allows you to:

  • access the overall picture of the shop floor schedule,
  • view and manipulate the load from each production operation scheduled to run through each operation, and
  • view and manipulate the schedule of a production order.

Keep in mind: Exact Visual scheduler can only be accessed if:

  • You have SE4010 — E-Special Order and option 103 in your license if your Exact Globe application is of product update 404 or you have SE4130 — Exact Visual Scheduler and option 118 in your license if your Exact Globe application is of product update 402 or 403.
  • The Operations check box is selected at System ? General ? Settings, under Manufacturing settings.
  • You have the Visual scheduler menu right at System ? HR & Security ? User rights.

To know more about Exact Visual scheduler, see below for the list of documents available:

How do I ...?

What version are you using?

The information in this document is applicable to product update 405 and higher. If you have versions lower than this, certain features explained here will not be applicable.

Toolbar

Fields

Related documents

     
 Main Category: Attachments & notes  Document Type: Online help main
 Category:  Security  level: All - 0
 Sub category:  Document ID: 22.567.942
 Assortment:  Date: 26-09-2022
 Release:  Attachment:
 Disclaimer