On this page, you can create or modify project deliverables. You can also create child projects.
To manage deliverables and work breakdown structure (WBS), function right 903 — Manage deliverable/WBS is needed. By default, users with the Project planner or Project administration role have this function right.
Note:
The information in this document is applicable to product update 260 and higher. If you have versions lower than this, certain features explained here will not be applicable.
Note: All fields with the “!” icon are mandatory.
A deliverable can be New, In progress, or Completed at any one time. However, the transitions that are allowed are displayed in the following:
Only project managers are allowed to change the status of the deliverables. The transitions of a parent deliverable will affect its child deliverables and vice versa. See the following tables for more information:
Status of parent deliverable
Status of child deliverable(s)
From New to In progress.
All will remain as New. This applies recursively down the tree.
From In progress to Completed.
All will change to Completed. This applies recursively down the tree.
From Completed to In progress.
All will remain as Completed. This applies recursively down the tree.
Status of child deliverable
Status of parent deliverable(s)
All will change to In progress. This applies to all parents up the tree.
All will remain as In progress. This applies to all parents up the tree.
If the status of the parent deliverable is In progress, the status will remain.
If the status of the parent deliverable is Completed, then this transition is not possible. The following message is displayed:
“The state of this deliverable can be changed to In progress only when the state of its parent deliverable is already In progress.”
These apply to all parents up the tree.
When you set a deliverable to the Completed status, a message will be displayed to notify the project manager of any incomplete request.
Click this to exit.
Click this to save the entry.
Click this to save the entry and create another deliverable.
Note: This button is available only when you are creating a deliverable.
Click this to delete the deliverable.
Note: This button is available only in the edit mode.
Click this to create a child project.
Note: This button is enabled only in the edit mode and disabled when you are creating a deliverable.
Type a code for the deliverable. This is mandatory.
Note: This is enabled only when you are creating a deliverable and disabled in the edit mode.
Type a description for the deliverable. This is mandatory.
Type or select an item to be linked to the deliverable. This is enabled only when you are creating a deliverable.
Type or select the parent deliverable (if any) for the deliverable.
Note: This is enabled only when you are creating a deliverable and disabled in the edit mode. This is mandatory.
This displays the name of the related project. This cannot be edited.
Type or select a date range for the deliverable.
Note: When creating an activity or material to be linked to this deliverable, the date range for the activity or material has to be within the date range defined in this field.
Select the status of the deliverable.