Exact Visual scheduler - Moving scheduled production operations
Menu paths
Manufacturing ➔ Planning ➔ Visual scheduler
Introduction
In this screen, you can move the operation that a production operation is scheduled to run through, to another timeframe.
What version are you using?
The information in this document is applicable to product update 405 and higher. If you have versions lower than this, certain features explained here will not be applicable.
How do I move a production operation to another operation?
- In the Selection: Production order screen, define the criteria to display only the production orders that you want to view in the scheduler.
- Click Start.
- You can move the production operation via the following ways:
- Click Op. zoom in at the toolbar. Select a scheduled production operation in the timeline, and then click Move at the toolbar.
- Click Op. zoom in at the toolbar. Click the scheduled production operation in the timeline, and then drag it to another timeframe.
- Click Op. zoom in at the toolbar. Right-click on a scheduled production operation in the timeline, and then click Move.
- Click Prod. zoom in at the toolbar. Select a scheduled production operation in the timeline, and then click Move at the toolbar.
- Click Prod. zoom in at the toolbar. Click the scheduled production operation in the timeline, and then drag it to another timeframe.
- In the Move step - Production order: [Production order ID] screen at the New operation field, select the operation that you want the selected production operation to move to.
- Select the Move to check box next to the Move start from field to define a new start date and time.
- Select the Move to check box next to the Move end from field
to define a new end date and time.
- At the Routing move options field, select the preferred move.
- Select the Show operation move check box to view the production operation in the Operation zoom in form after it has been moved.
- Click OK.
Keep in mind: If the schedule of the operation is finite, you will see a Next button instead. To find out if the schedule of an operation if finite or not, go to Manufacturing
? Setup ? Operations, select the operation, and then click Open. The schedule of the operation is finite if the Finite schedule check box under the Capacity/Scheduling tab is selected. If the schedule of the operation is finite, proceed to step 10.
- Click Next to move the production operation to the defined start or end date and time.
Tabs
Destination information tab
New operation
Type or select the ID of the operation to specify the new operation that the production operation will run through.
Move start from, Move to
The Move start from field displays the current date and time that the production operation is scheduled to start. To change the start date or time, select the Move to check box, and then type or select the new start date or time.
Move end from, Move to
The Move end from field displays the current date and time that the production operation is scheduled to end. To change the end date or time, select the Move to check box, and then type or select the new end date or time.
Move - allow overload of finite operation
Select this check box if you want the production operation to move to a new timeframe. The other production operations scheduled to run through the operation during that timeframe are not rescheduled, even if it results in the load on the capacity of the operation to go over 100%. This check box is displayed only if the source operation is finite.
Routing move options
- Move this step only — Select this to move only the selected production operation.
- Include previous steps — Select this to move the selected production operation and all production operations before it.
- Include subsequent steps — Select this to move the selected production operation and all production operations after it.
- Move entire routing — Select this to move the selected production operation and all other production operations.
Show operation on move
Select this check box if you want to view the production operation in the Operation zoom in form after it has been moved.
Routing settings tab
Original operation
This displays the original operation the production operation was scheduled to run through.
New operation
This displays the new operation the production operation will be moved to.
Planned qty
This displays the quantity of the make items being made on the production.
Realized qty
This displays the quantity of make items that have been completed on the production operation.
Promised date
This displays the promised date of the first open delivery line on the production operation.
Rem setup hrs
This displays the remaining setup hours of the production operation.
Rem run hrs
This displays the remaining run hours of the production operation.
Total hours
This displays the estimated amount of time needed to set up the operation and run the production operation through it.
Resources to use
Type the number of machines in the operation that the production operation will run through or the number of employees who will work on the production operation during its scheduled timeframe.
Buttons
Next
Click this to move the production operation to the defined start or end date and time.
Cancel
Click this to cancel the move and return to the Visual scheduler screen.
Related documents
Main Category: |
Attachments & notes |
Document Type: |
Online help main |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
22.593.268 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |