Exact Visual scheduler - Viewing operation details

Menu paths

Manufacturing Planning Visual scheduler

Introduction

In this screen, you can review important details about the production operations. These details include the production quantities, scheduled start and end dates and time, linked or not linked BOM items, and the planned, realized, and projected hours.

What version are you using?

The information in this document is applicable to product update 405 and higher. If you have versions lower than this, certain features explained here will not be applicable.

How do I view another operation linked to the production order?

  1. In the Selection: Production order screen, define the criteria to display only the production orders that you want to view in the scheduler.
  2. Click Start.
  3. You can view another operation linked via the following ways:
    • Click Op. zoom in at the toolbar. Select a scheduled production operation in the timeline, click Review, and then click Operation details.
    • Click Op. zoom in at the toolbar. Right-click on a scheduled production operation in the timeline, and then click Operation details.
    • Click Prod. zoom in at the toolbar. Select a production order to be displayed in the timeline, and then click Details.
  4. In the Operation details screen at View another OP, select the required operation.
  5. Click OK.

How do I change the status of the production operation?

  1. In the Selection: Production order screen, define the criteria to display only the production orders that you want to view in the scheduler.
  2. Click Start.
  3. You can change the status of the production operation via the following ways:
    • Click Op. zoom in at the toolbar. Select a scheduled production operation in the timeline, click Review, and then click Operation details.
    • Click Op. zoom in at the toolbar. Right-click on a scheduled production operation in the timeline, and then click Operation details.
    • Click Prod. zoom in at the toolbar. Select a production order to be displayed in the timeline, and then click Details.
  4. In the Operation details screen, click the General tab.
  5. At Status, select the required status.
  6. Click OK.

How do I change the actual start date of the production operation?

  1. In the Selection: Production order screen, define the criteria to display only the production orders that you want to view in the scheduler.
  2. Click Start.
  3. You can change the actual start date of the production operation via the following ways:
    • Click Op. zoom in at the toolbar. Select a scheduled production operation in the timeline, click Review, and then click Operation details.
    • Click Op. zoom in at the toolbar. Right-click on a scheduled production operation in the timeline, and then click Operation details.
    • Click Prod. zoom in at the toolbar. Select a production order to be displayed in the timeline, and then click Details.
  4. In the Operation details screen, click the General tab.
  5. At Actual start, type and select the date and time that the production operation actually began.
  6. Click OK.

Fields

Tabs

Buttons

Related documents

     
 Main Category: Attachments & notes  Document Type: Online help main
 Category:  Security  level: All - 0
 Sub category:  Document ID: 22.590.469
 Assortment:  Date: 26-09-2022
 Release:  Attachment:
 Disclaimer