E-WMS - Picking advice setting 'SB advice policy' (until release 407)
Introduction
This document describes the E-WMS setting 'SB advice policy'
(Serial/batch advice policy), available in several E-WMS module settings, until
product update 407.
For the changed advice settings as per product update 408, view
this
document.
Description
The setting 'SB advice policy' is used in E-WMS settings available through
menu System, General, Settings, for
following settings tabs:
- WMS Sales Order Fulfillment
- WMS Replenishment
- WMS Production Issues
This setting is part of the picking advice settings and allows you to
configure what batches or serial numbers should be picked first. The oldest
dates will always be selected first.
In Exact Globe Next and E-WMS, a serial/batch end date can be left empty, a start date is
always filled.
- End date or else start date
The oldest batches are selected by looking at the S/B
end date.
For batches with an empty end date, end date '31-12-2299' is applied (so
probably advised after batches with specific end date), and the start date
is also applied now for these batches without end date.
- Sample
batch B1 start date 01-01-13 end date
31-12-2014
batch B2 start date 01-02-13 end date
31-12-2014
batch B3 start date 01-12-12 end date
(empty)
batch B4 start date 01-11-12 end date
(empty)
batch B5 start date 01-12-11 end date
01-01-2015
Advice generated (at 01-01-14):
For batches B3 and B4 end date '31-12-2299' is applied, and batch B4 will be
advised first because of the older start date.
Order of advising these batches: B1, B2 (or: B2, B1 - since equal end date,
will depend on location policy), B5, B4, B3
- End date and also start date
The oldest batches are selected by looking at the combination of end
date + start date.
In case you would produce batches with the same end during an entire month,
you will still advice the batches produced at first of the month, before
batches produced by the end of the month.
An empty end date will be interpreted as '31-12-2299', so will be advised
last.
- Sample
batch B1 start date 01-01-13 end date
31-12-2014
batch B2 start date 01-02-13 end date
31-12-2014
batch B3 start date 01-12-12 end date
(empty)
batch B4 start date 01-11-12 end date
(empty)
batch B5 start date 01-12-11 end date
01-01-2015
Advice generated (at 01-01-14):
For batches B3 and B4 end date '31-12-2299' is applied.
Order of advising these batches: B1 (since older start date than B2), B2,
B5, B4, B3
- End date
Stock is selected by the S/B end date. An empty end date is
regarded as '31-12-2299', so will be advised last.
- Sample
batch B1 start date 01-01-13 end date
31-12-2014
batch B2 start date 01-02-13 end date
31-12-2014
batch B3 start date 01-12-12 end date
(empty)
batch B4 start date 01-11-12 end date
(empty)
batch B5 start date 01-12-11 end date
01-01-2015
Advice generated (at 01-01-14):
For batches B3 and B4 end date '31-12-2299' is applied.
Order of advising these batches: B1, B2 (or: B2, B1 - since equal end date,
will depend on location policy), B5, B3, B4 (or B4, B3 - depending location
policy)
- Start date
Stock is selected by the S/B start date.
- Sample
batch B1 start date 01-01-13 end date
31-12-2014
batch B2 start date 01-02-13 end date
31-12-2014
batch B3 start date 01-12-12 end date
(empty)
batch B4 start date 01-11-12 end date
(empty)
batch B5 start date 01-12-11 end date
01-01-2015
Advice generated (at 01-01-14):
Order of advising these batches: B5, B4, B3, B1, B2
Related documents
Main Category: |
Attachments & notes |
Document Type: |
Support - On-line help |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
25.825.545 |
Assortment: |
E-WMS
|
Date: |
24-12-2020 |
Release: |
|
Attachment: |
|
Disclaimer |
|
|