Exact Visual scheduler - Viewing history of moved production operations
Menu path
Manufacturing ➔ Planning ➔ Visual scheduler
Introduction
In this screen, you can view the history of all production operation moves performed.
What version are you using?
The information in this document is applicable to product update 405 and higher. If you have versions lower than this, certain features explained here will not be applicable.
How do I view the history of moved production operations?
- In the Selection: Production order screen, define the criteria to display only the production orders that you want to view in the scheduler.
- Click Start.
- In the Visual scheduler screen, click Op. zoom in at the toolbar.
- Click Review.
- Click Move history.
Columns
Production order
This displays the IDs of production operations that were moved.
Step
This column displays the IDs of the steps being performed in the operation.
Old start
This displays the scheduled start dates and times before the production operations were moved.
New start
This displays the new scheduled start dates and times of the production operations.
Old operation
This displays the IDs of the operations that the production operations were scheduled to run in, before the move.
New operation
This displays the IDs of the operations that the production operations were moved to.
Button
Close
Click this to exit.
Related documents
Main Category: |
Attachments & notes |
Document Type: |
Online help main |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
22.595.385 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |